Central Community Schools - Building the Future!

Cafeteria

Concrete block at cafeteria building start August 2011.

 

Intermediate School

Brick at Intermediate school starts August 2011.

 

Intermediate School

Sheet rock finish at intermediate school starts September 2011.

 

Gymnasium

Concrete slab poured at gym June 16, 2011.

Middle School

Structural steel installation begins June, 01, 2011.

 

Intermediate School

Building A exterior sheathing board installation started May 25, 2011.

Middle School

Building D & E concrete slab poured May 16, 2011.

Middle School

Building F concrete slab poured May 21, 2011.

Intermediate School Building A

Metal studs and fire proofing started May 2, 2011.

 

Intermediate School Building A

Intermediate School  Building A plumbing and ductwork start April 4, 2011.

Intermediate School Building A

Intermediate School  Building A second floor deck is poured April 29, 2011.

Cafeteria Building

Cafeteria Building Structural Steel erection starts April 29, 2011.


.

Intermediate School Building B & C

Intermediate School  Building B and C structural steel erection starts April 6, 2011.

Intermediate School  Building B and C concrete slab poured April 4, 2011.

Intermediate School

Cafeteria building concrete slab pooured March 21, 2011.

Intermediate School

Steel erection starts on Building "A", March 10, 2011.

Structural Steel Delivered

Structural Steel delivered March 9, 2011 for Intermediate School.

CCSS Demolition Begins

Crane Delivery

Crane delivered March 1, 2011.

CCSS Groundbreaking Ceremony

Cafeteria

Cafeteria building construction starts February 20, 2011.

Award of Construction Recommended to Board

On Thursday, August 12th, Central Community School System administration presented its recommendation to the School Board for the award of the Building Construction Package. Seven bids were received on July 15 at 3:30pm. The bids were very close in range       and the School System is very pleased with both the number and quality of bids received.

Thursday August 12th, 2010

The building construction package was awarded to :

Arkel Constructors, Inc. / Roy Anderson Corp.

A Joint Venture #2 D/B/A

Arkel Anderson Joint Venture

 

Base bid was                $31,000,788.00

Alternate #1                  $990,000.00

Alternate #2                  $990,000.00

Contract Sum               $32,980,788.00

 

Constructing alternate #1 and alternate #2 will enable the School System to build both the New Intermediate School and the New     Middle School to their designed capacity of 1,200 students per each campus for a total of 2,400 students for grades 3 thru 8.