Central Community Schools - Building the Future!
![]() |
CafeteriaConcrete block at cafeteria building start August 2011. |
|
![]() |
Intermediate SchoolBrick at Intermediate school starts August 2011. |
|
![]() |
Intermediate SchoolSheet rock finish at intermediate school starts September 2011. |
|
![]() |
GymnasiumConcrete slab poured at gym June 16, 2011. |
![]() |
![]() |
Middle SchoolStructural steel installation begins June, 01, 2011. |
|
![]() |
Intermediate SchoolBuilding A exterior sheathing board installation started May 25, 2011. |
![]() |
![]() |
Middle SchoolBuilding D & E concrete slab poured May 16, 2011. |
![]() |
![]() |
Middle SchoolBuilding F concrete slab poured May 21, 2011. |
![]() |
![]() |
Intermediate School Building AMetal studs and fire proofing started May 2, 2011. |
![]() |
![]() |
![]() |
|
![]() |
Intermediate School Building AIntermediate School Building A plumbing and ductwork start April 4, 2011. |
![]() |
![]() |
Intermediate School Building AIntermediate School Building A second floor deck is poured April 29, 2011. |
![]() |
![]() |
Cafeteria BuildingCafeteria Building Structural Steel erection starts April 29, 2011.
|
![]() |
![]() |
Intermediate School Building B & CIntermediate School Building B and C structural steel erection starts April 6, 2011. Intermediate School Building B and C concrete slab poured April 4, 2011. |
![]() |
![]() |
Intermediate SchoolCafeteria building concrete slab pooured March 21, 2011. |
![]() |
![]() |
Intermediate SchoolSteel erection starts on Building "A", March 10, 2011. |
![]() |
|
|
Structural Steel DeliveredStructural Steel delivered March 9, 2011 for Intermediate School. |
|
|
|
Crane DeliveryCrane delivered March 1, 2011. |
|
|
|
CafeteriaCafeteria building construction starts February 20, 2011. |
|
Award of Construction Recommended to BoardOn Thursday, August 12th, Central Community School System administration presented its recommendation to the School Board for the award of the Building Construction Package. Seven bids were received on July 15 at 3:30pm. The bids were very close in range and the School System is very pleased with both the number and quality of bids received. Thursday August 12th, 2010 The building construction package was awarded to : Arkel Constructors, Inc. / Roy Anderson Corp. A Joint Venture #2 D/B/A Arkel Anderson Joint Venture
Base bid was $31,000,788.00 Alternate #1 $990,000.00 Alternate #2 $990,000.00 Contract Sum $32,980,788.00
Constructing alternate #1 and alternate #2 will enable the School System to build both the New Intermediate School and the New Middle School to their designed capacity of 1,200 students per each campus for a total of 2,400 students for grades 3 thru 8. |
||